Construction
Update as of December 15, 2005
Construction continues in Building 2 as detailed
below. Some activites are delayed beyond December 19 and should be completed
by the end of December.
Construction
Update as of November 29, 2005
Construction
is taking place in Building 2 from November 21 through approximately December
19. Activities include:
- Cafeteria: paint, carpet, cabinetry, tile
- First
Floor: New carpet and paint on part of the floor
- Third
Floor: New carpet and paint on part of the floor
- Data Center: New paint
Construction
Update as of September 6, 2005
Major
construction has been completed in Building II. However,
there will be minor construction follow-up activities taking
place over the next two months, to include:
- Punchlist
items required to complete recent construction on the
LL, 1st, 2nd & 3rd
floors
- Corridor carpeting
on the LL, 1st and 3rd floors in areas adjacent to recent construction
(to take place off-hours to limit disruption to staff in the
building)
- Cafeteria
renovations to include new carpet & paint (furniture
additions are also expected in the upcoming months)
- Updating finishes
in the elevator cabs
Construction
Update as of June 20, 2005
- There will be construction on the first floor, as well as the Lower Level,
2nd and 3rd floors.
- First floor renovations will include accomodations
for academic programs, as well as cafeteria modernization (carpet and
paint).
- Schedule updates:
- Third Floor (ISS): In process through July
- Construction of LL, South-East Side (READI): In process through
June
- Second Floor (Comptroller): In process through mid-August
- First Floor Renovations: mid-July through mid-August
Construction Information as of May 6, 2005
Construction Locations
There will be extensive renovations
to the Lower Level, as well as the 2nd and 3rd floors of Building 2.
Purpose of the Construction
Construction is
planned in order to accommodate both the relocation of READI
to the lower level and the relocation of administrative departments from
Foggy Bottom to the Virginia Campus (Information Systems & Services
(ISS) and Comptrollers office staff during the summer and
fall, respectively).
Construction Schedule
Based on current requirements & estimations, construction
activities began the week of May 9th.
The following is a general schedule for construction in the building during
the upcoming months:
- May–late-July
2005: Construction on 3rd floor (ISS)
- May–mid-June
2005: Construction of LL, South-East Side (new READI space)
- late-June–mid-August
2005: Construction on 2nd Floor, remainder
(Comptroller’s office)
Construction Hours
Construction activities will generally occur Monday through Friday,
during the hours of 6am – 2pm.
Potential Disruptions
We are working to limit the disruption
caused by this construction, however, as is true with all construction activities—and
particularly activities of this magnitude—there will be increased
noise and disturbances in the building during this timeframe. When appropriate,
notices about these disturbances will be posted on all entrance doors and
in elevator lobbies.
Risk Management
We will be working with Risk
Management to ensure that the proper safety measures are in place throughout
this construction project.
Other Resources
Check out
the website designed
to help employees being transferred to the Virginia Campus.
Check
out positions available at the Virginia Campus. Search by location "Virginia."
Questions:
If you have any questions regarding this schedule or the construction activities
that will be occurring in the building, please contact Alicia
O'Neil, Project
Manager x42371 or Bob Minnis at
or x63510.
|